A MAJOR transformation of Saltash’s waterfront is gathering pace as new rock defences continue to be installed to help protect Jubilee Green from coastal erosion.
Contractors have now completed the first section of the new rock armour along the shoreline, reaching the 115-metre point.
Work has since moved on to removing the old pre-cast concrete revetment between the 115m and 120m marks, clearing the way for the next section of rock armour to be installed in the coming days.
The project will see approximately 4,000 tonnes of rock delivered to Jubilee Green as part of a major overhaul of the coastal defences.
The existing revetment, which protects the boat park, open green space and car park, had deteriorated to the point where it was considered to be failing.
The new rock armour is designed to provide a long-lasting barrier against coastal erosion by absorbing and reducing the force of waves hitting the shoreline.
The work involves removing the failed concrete and reshaping the bank before a geotextile membrane and smaller stones are installed. Large armour rocks are then carefully positioned on top, creating an interlocking structure designed to withstand the power of the water.
Where possible, material removed from the old revetment will be reused as part of the new defence.
The project has also been designed with the area’s environment in mind. Jubilee Green sits within the SSSI Impact Risk Zone for the Tamar Tavy Estuary, which is protected for its biological and geological importance.
The gaps between the new rocks are expected to provide shelter and habitat for marine life, with species such as crabs, mussels, barnacles and shellfish able to establish themselves over time.
Public access remains restricted while the work continues. Construction began on May 18 and is scheduled to take around 20 weeks, after which the surrounding area will be reinstated.